How long a full flat renovation takes: phases and timelines

· 6 min

Worker checking a wall is flat with a spirit level during a renovation

The building work on a full renovation of a 70–80 m² flat in Barcelona usually takes 10 to 16 weeks, provided materials arrive on time and the building hides no surprises. Before that comes the quote, the municipal paperwork and material orders, which can add anything from a few weeks to several months if the job needs a licence. What drags a renovation out most isn’t the work, it’s the waiting.

The full timeline, from visit to handover

Guide timings for an average flat with one bathroom and one kitchen, without structural changes:

PhaseGuide duration
Visit, measurements and written quote1–2 weeks*
Works notification (interior work)depends on procedure*
Licence with technical projectseveral months*
Demolition and rubble1–2 weeks*
Partitions and installations3–4 weeks*
Plastering, screeds and drying2–3 weeks*
Tiling, flooring, bathroom and kitchen3–4 weeks*
Joinery, painting and finishing2–3 weeks*
Total on site, 70–80 m² flat10–16 weeks*

*Guide timings. Some phases overlap, which is why the total isn’t the exact sum. We give you your job’s schedule in writing with the quote.

Before work starts: quote, paperwork and orders

The weeks beforehand decide whether the job runs smoothly. First, the visit and the itemised quote. Then the paperwork: if the renovation is interior and doesn’t touch the structure, façade or communal elements, in Barcelona a comunicado de obras (works notification) filed online is usually enough; if a load-bearing wall has to be opened or the façade touched, you need a technician, a project and a licence, and that procedure can take months. Timings and requirements change, so confirm them with the Ajuntament (city council) or ask us during the visit.

In parallel, it pays to finalise the materials list and order whatever takes time. These are guide lead times we often see, although they depend on each supplier and the time of year:

MaterialGuide lead time
Made-to-measure exterior windows4–8 weeks*
Kitchen units3–6 weeks*
Interior doors3–6 weeks*
Tiles or flooring to order2–6 weeks*
Worktop, from template1–2 weeks*
Made-to-measure shower screen, from measuring1–3 weeks*

*Guide supplier lead times. The worktop and shower screen can only be measured once the units or tiling are in place, so their wait is part of the on-site schedule.

The job, week by week

  • Week 0: notice to the building administrator, protection of stairs and lift, supplies cut off in the flat and authorisation if the street has to be occupied with bulk bags or a skip.
  • Weeks 1–2: interior demolition and rubble removal. It is the noisiest phase and the one that reveals the real state of beams, walls and pipes.
  • Weeks 2–4: setting out the new layout on the floor, brick or plasterboard partitions and chases for the installations.
  • Weeks 3–6: plumbing, drainage, electrics and ventilation. Before walls are closed, the pipes are pressure-tested and we check the position of sockets and light points with you.
  • Weeks 5–7: plastering, levelling walls and floor screeds. Mortars and screeds need to dry before flooring goes down.
  • Weeks 7–10: waterproofing of bathroom and kitchen, wall and floor tiling.
  • Weeks 9–12: kitchen installation, worktop template, interior doors and first coats of paint.
  • Weeks 11–14: sanitaryware, taps, switches and sockets, shower screen, final coat of paint, cleaning and a walk-through with your snagging list.

In a 100 m² flat or one with two bathrooms, each phase stretches and the total moves towards the top of the range. In a small flat in Sant Antoni or Sants with no layout changes, it can stay at the lower end.

What stretches timelines in an older building

  • Damaged beams or sagging floors: that area has to stop until a technician decides on the reinforcement.
  • Asbestos in downpipes, tanks or fibre-cement sheets, common in buildings from before 2002: removal is done by a firm registered in the RERA with an approved work plan, and that plan has its own timings.
  • Lead pipes up to the meter or in the riser: those in the flat belong to the owner, but if the riser has to be touched it is the community’s matter and needs coordinating with them.
  • Floors and ceilings being restored: hydraulic tiles or original cornices need manual work and longer drying times.
  • Difficult access: with no lift, or in Ciutat Vella streets where loading and unloading is restricted, every movement of material takes longer.
  • Changes of mind: moving a socket once the wall is closed or changing the tile after ordering it costs days.

How to shorten the job without lowering quality

  • Finalise the layout and materials list before demolition.
  • Order windows and kitchen as soon as you have accepted the quote.
  • Respect drying times: rushing a screed or waterproofing is the quickest way to have problems later.
  • Have a single point of contact who coordinates all the trades, so the plumber isn’t waiting for the electrician or the tiler for the plasterer.
  • Keep a margin in the schedule for what only shows up once walls are opened.

If you are planning a full renovation and need realistic dates, tell us the floor area and what you want to change. We reply within 24 working hours, come to see the flat and send you the itemised quote and phased schedule in writing. Our own team does the work, with one person in charge from start to finish.

Frequently asked questions

Questions on this topic

As a guide, 8 to 12 weeks on site if there are no major layout changes or surprises in the building. Add the time beforehand for the quote, paperwork and material orders.

Usually not, at least during demolition and the installations: there will be water and power cuts, dust and rubble. It is best to plan somewhere else to stay for the whole job or, at the very least, for its first weeks.

It depends on the procedure. Interior work that doesn’t touch the structure usually goes through a works notification, which is quick; if a licence with a technical project is needed, allow several months. Confirm the procedure and timings with the Ajuntament or with us.

Waiting for materials and changing decisions halfway through, more than the work itself. Made-to-measure windows and kitchens in particular are best ordered before work starts.

Yes. Along with the itemised quote we give you a phased schedule, and if something turns up once walls are opened that changes the timings, we explain it and update the schedule in writing.